Contract register: cancellation notices, tacit renewals and the dates not to miss
Tacit renewal gives no warning: if the cancellation does not arrive in time, the contract renews for another term. How to count the right date, and what to put in the register.
General information, not legal, tax or technical advice: for your own case, check the rules cited with a professional.
#The problem
A company's contracts — software, rentals, maintenance, subcontracts, insurance policies — almost all renew on their own unless someone cancels them within a notice period. That period is written in a clause, in days or months, and falls well before the expiry. By the time anyone notices, the cancellation window has often already closed: the contract renews for another year, or two.
#How to count the cancellation date
- Find the expiry of the current term and the renewal length written in the contract.
- Find the notice period, as written: in days or in months. Do not convert months into days; they are counted as months.
- Subtract the notice from the expiry. The result is the last useful day.
- Move it at least one day earlier. A cancellation takes effect when it reaches the recipient, not when it leaves (artt. 1334–1335 c.c.): it should arrive before the last day.
- Note the means the clause requires: usually PEC or registered letter with return receipt.
Example: a subcontract expiring on 30 September with 60 days' notice. Sixty days before 30 September is 1 August; with one day's margin, the cancellation must leave by 31 July.
#What to put in the register
For each deadline, a row with:
- the computed date and the date as written on the document;
- the counterparty and the amount, if any;
- the file and the page or clause it comes from;
- the calculation made and the rule it rests on;
- the days left and the reminder date;
- whether it falls on a Saturday, a Sunday or a holiday;
- «to confirm», when the date cannot be read with certainty.
The obligations that cannot be dated go in a separate list: they are the ones that get lost.
#Not only contracts
The same register should hold:
- Policies: after the premium's due date, cover lasts 15 days (art. 1901 c.c.), then it is suspended. The tacit renewal of a policy cannot exceed two years (art. 1899 c.c.).
- DURC: valid 120 days from the request.
- F24: if the due date falls on a Saturday or a holiday, it is paid on the next working day.
- Permits, certificates, invoices coming due.
#An example
In the recorded example a building site's deadline sheet, read on 1 April, holds 10 deadlines, one already past and two undated. The liability policy expired on 15 March: the 15-day grace period ended on the 30th, so since 31 March the site has been without cover. The subcontract with 60 days' notice must be cancelled by 31 July, and the letter is already drafted. Two F24 payments due on Saturday 16 May are paid on Monday 18.
#What the agent does beside your ERP
The Contract and deadline register AI agent reads contracts, policies, permits, certificates, DURC and invoices — PDFs, scans, Word, CSV exports — up to 30 files at a time. The model reads only the written facts; every date is computed by code, with the rule beside it. It returns the register in Excel, an .ics calendar to import with the reminder appearing 15 days before (you change it), and for each tacit renewal a cancellation letter in Word with the date by which it must arrive.
The letter is a draft: you check it, sign it and send it, by PEC or registered letter. The agent sends nothing and is not legal advice: the final check on the clauses is the lawyer's.
The agent and its example are on the Contract and deadline register page; the other agents for law firms are under law firms. For the time limits that come from writs and PEC see the guide to court deadlines and the one on the avviso bonario.
#Frequently asked questions
#By when must I cancel a tacitly renewing contract?
By the expiry minus the notice written in the clause, and so that the cancellation arrives in time: the date of receipt counts, not the date of sending. Better keep at least one day's margin.
#Is a notice period in months converted into days?
No. Three months' notice is counted in months from the expiry, not as 90 days.
#How long is the DURC valid?
120 days from the date of the request.
#Does the agent send the cancellation to the supplier?
No. It prepares the letter as a draft with the date by which it must arrive; you approve it and send it, by PEC or registered letter.
The agent that does this job
The steps above are what the Contract and deadline register agent applies on every run: open it to see what it takes in, what it checks and what it hands back.
More guides
- Italian court deadlines from served acts and PEC: how they are counted
- Splitting condominium expenses on the millesimal tables
- Splitting heating costs: fixed share and consumption share (30/70)
- Declaration of conformity (D.M. 37/08): what to attach and what to check
- AML customer due diligence for accountants in Italy: the steps